Lession 5: Farm Shack layout, storage, electrical system installation and the water supply and drainage

a. prepare the shack camp
All infrastructure including: camp Shack and the ancillary construction contractors are concentrated near the right online safety RADIUS outside blasting.
 
b. electricity and water service construction
The contractor will contract with the local power bodies where power lines had come over to serve construction and will use 250 KVA generator in the event of lost power grid. Water source will use the water truck to combined with the irrigation pump washing and watering the moisture during construction of road surface Foundation layer.
 
c. the Volume of materials, construction equipment
The contractor will build the warehouses to the material in the range obtained investor, consultant as well as the relevant unit. The storing of materials will be constructed in a logical manner to the gathering of materials is easy and convenient for installation.
 
d. the goal of surface water and groundwater
Prior to construction contractors will ensure keeping the ground works, foundation pits, dumps land grab by a dry ditch system always objective, target track (surface water), water collection wells pumping pepper (ground water).